A production bill of material (BOM) holds master data that describes the components and subassemblies used in the production of a parent item. Once a production order is created for that parent item, its production BOM will govern the calculation of material requirements as represented in the Prod. Order Components window.
Dynamics NAV also support assembly BOMs. You use assembly orders for making end items from components in a simple process that can be performed by one or more basic resources, which are not machine or work centers, or without any resources. For example, an assembly process could be to pick two wine bottles and one coffee sack and then pack them as a gift item. For more information, see the "Assembly BOMs or Production BOMs" section in How to: Work with Bills of Material.
Before you can set up a routing, the following must be in place:
To edit the BOM, set the Status field to New or Under Development. To activate it, set the Status field to Certified.
Proceed to fill in the production BOM lines.
In the Scrap % field you can enter a fixed percentage of components that are scrapped during production. When the components are ready to be consumed in a released production order, this percentage will be added to the expected quantity in the Consumption Quantity field in a production journal. For more information, see How to: Register Consumption and Output.
This scrap percentage represents components that are scrapped during production when picking from inventory, whereas the scrap percentage on routing lines represents scrapped output before putting on inventory.
In the Routing Link Code field, enter a code to connect the component to a specific operation. For more information, see the "To create routing links" section in How to: Create Routings.
To recalculate the item’s standard cost from the item card, choose the Manufacturing action, and then choose the Calc. Standard Cost action.
New versions of production BOMs are used when, for example, an item is replaced by another item, or when a customer requires a special version of a product. The version principle enables various versions of a production BOM to be managed. The structure of the production BOM version corresponds to the structure of the production BOM. The basic difference is in the time validity of the versions. The validity is defined by the starting date.
The starting date indicates the start of the period in which this version is valid. For all other considerations, the starting date is a filter criterion for calculations and evaluations. The BOM version is valid until the next version becomes valid for its starting date.
In the Version Code field, enter the unique identification of the version. Any combination of numbers and letters is permitted.
The newly created version is automatically assigned the status New.
The time validity of the version is specified by the Starting Date field.
Select the Item option in the Type field to use an item from your item master data in the production BOM. If the item also has a production BOM, whereby the Production BOM No. field is filled in on the item card, this production BOM is also considered.
Select the Production BOM option if you want to use a phantom production BOM on the line.
Phantom production BOMs serve for structuring products. This production BOM type never leads to a finished product, but is used exclusively for determining the dependent demand. Phantom production BOMs do not have their own item master data.
The quantity is calculated taking into consideration different dimensions which are also entered on the production BOM lines. The dimensions refer to an order unit of the respective item. The length, width, depth and weight can be entered as dimensions.
The Calculation Formula, Length, Width, Depth and Weight columns are not displayed, because they are only used by some users. If you wish to use the calculation of the quantity, you must first display these columns.
The relation of the individual components is defined by the calculation formula. The following possibilities are available as a calculation formula:
In a production BOM, seventy metal parts with the dimensions length = 0.20 m and width = 0.15 m are required. The values are entered as follows: Calculation Formula = Length x Width, Length = 20, Width = 15, Quantity per = 70. The quantity is given by the Quantity per x Length * Width, that is, Quantity = 70 x 0.20 m x 0.15 m = 2.1 m2.
How to: Create Routings
Setting Up Manufacturing
Manufacturing
Planning
Inventory
Purchasing
Working with Dynamics NAV
© 2017 Microsoft. All rights reserved.